Building a new deck from scratch is always a challenge, but this one was on the sloping downhill. Our experienced team had to face few issues, due to the slope they had to dig footing much deeper than originally requited BY THE CODE depth, plus, slope made it very difficult to get any heavy EQUIPMENT DOWN to the site.
Building DOUBLE-DECK requires extra attention to details, and to the frame structure so that it will support all this weight.
All challenges accomplished we built a huge-deck without many complications, in a timely manner, took us only 2 months with inspections and COVID-19 related delays.
About The Project
New Build Wood Double-Deck
project date
27 May.- 10 Aug. 2020
client name :
Ms. Ally M. and Amber
Materials :
Floor:
Treated Wood
Railing:
Treated wood
Lighting: N/A
Location:
Morristown, New Jersey
budget :
$56,000